AMERICAN REGIONAL CENTER FOR ENTREPRENEURS

ARCFE GROUP 10 PROJECT PROGRESS

Oct 2018

The site visit in Oct 2018 is summarized as follows:

 

– The foundation piles are mostly complete. The entire foundation work has completed 60%, and is expected to be completed by Nov 2018.

July 2018

The site visit in July 2018 is summarized as follows:

Ground excavation work has been made in good progress.

– The porject is still carrying out foundation work with the supporting piles being completely completed.

– The foundation piles are well in construction. The entire foundation work is expected to be completed in the first half of 2018.

April 2018

The site visit in April 2018 is summarized as follows:

Ground excavation work has been made in good progress.

– The porject is carrying out foundation work and the supporting piles have been substaintially completed.

– The foundation piles are currently being built. The entire foundation work is expected to be completed in Q3 2018.

December 2017

We stopped by the job site on 12/21/2017 and checked out the project progress as follows:

– The demolition is completely completed. Ground excavation work in progress.

September 2017

We stopped by the job site on 9/6/2017 and checked out the project progress as follows:

– The demolition is almost completed except the subsurface area;

– The developer has settled construction loan and expects to close in November.

June 2017

As of June 2017, the project has submitted demo permit and received DOB approval. The issuance is now subject to MTA approval. All the new building plans have been submitted to the DOB for review.