December 2017

Job site is continuing to making good progress as of 12/28/2017 as follows:

– Since last quarter visit in October, foundation has been completed and superstructure is on its way up to 3rd floor.

– Despite of cold weather, over 30 concrete workers are currently doing rebar and form works and plan to pour concrete this weekend.  It is anticipated whole building superstructure will be completed by end of January or early February.

– Sidewalk bridge and scaffold is in place. Protection to adj parking lot has been erected as well.
– Electrical subcontractor is applying for temporary power on site.
– In next few weeks, the GC will commence partition metal stud framing and mechanic, and plumbing works.


September 2017

Job site is continuing to making good progress as of 10/17/2017 as follows:

– Pile is basically complete except remaining piles in elevator pits to be grouted when we begin to work there later.

– All footing and foundation walls are in place.  There are more pile cap works and elevator pit to be finished in next two to three weeks depending how fast we excavate the pit area and then dewatering.

– Temporary power installation was completed this week.

– The GC is targeting to finish all pile caps and below grade slab by first week of November.

June 2017

Per site visit on 6/20/2017, a summary of work is as below:

Demolition has been completed. Job site has been mobilized and Lions Group plans to break ground next week.

March 2017

Per site visit on 3/31/2017, here is summary of finding:

  • old building’s superstructure has been demolished;
  • sidewalk bridge has been dismantled last week;
  • basement has been demolished and they already knocked down old foundation;
  • Overall, the demolition has been done. Excavation is going to commence soon.


ARCFE visited construction site on 2/6/2017. Per today’s visit, over a dozen of workers on site and two excavators. 1st floor is almost demolished. Today, our monitoring company sent their worker to put up four crack monitoring devices onto adj. interior wall.   We should come back to check it tomorrow and then we will come to check it periodically thereafter. Going forward, we will pay them $1,000 per month until we finish our superstructure.  We shall finish up demolition in next two to three weeks.


As of 9/30/2016, asbestos fibres have been cleaned. Utilities were cut off. GC is going to demolish superstructure.

JUNE 2016

Land title was officially transferred on May 18th 2016. As site visit on July 8th 2016, demolition of old building has started.