ARCFE GROUP 8 PROJECT PROGRESS

September 2017

75 Park Lane

Superstructure concrete work is underway and has been poured up to the 9th  floor of the tower level. Tower logistics are in place and cycle times as sped up 1 day per floor.  Permanent MEP utility installation continues on the ground floor and interior wall layout has begun on the 2nd floor.

Shore House

Superstructure concrete work is underway and has been poured up to the 3rd floor. Concrete work is ongoing.

June 2017

75 Park Lane

As of the end of July, foundation activity for 75 Park Lane is finished. Superstructure concrete work is underway and has been poured up to the 2nd floor.

Shore House

As of the end of July, foundation activity for Shore House is finished. Superstructure concrete work is going to start.

March 2017

75 Park Lane:

Foundation activity for 75 Park Lane is ongoing. As of 2017Q1, the pile driving work is finished. Concrete pile caps and grade beams are being poured, and temporary electrical service is being installed.

2 Shore:

Foundation activity for Shore House is ongoing. As of 2017Q1, the pile driving work is finished. Concrete pile caps and grade beams are being poured, and temporary electrical service is being installed.

DECEMBER 2016

75 Park Lane

The construction for 75 Park Lane started in 2016Q4, and the foundation activity is ongoing. As of the end of Dec 2016, about 50% of piles were installed.

Shore House

The construction for Shore House started in 2016Q4, and the foundation activity is ongoing. As of the end of Dec 2016, about 15% of piles were installed.

OCTOBER 2016

75 Park Lane received foundation permit in early October. Strategic Capital held an official Ground Breaking Ceremony on 10/27/2016. On the day of ceremony, we saw that the excavation of 75 Park Lane has already started.

Developer told us that 2 Shore Drive North will receive its foundation permit in November. They will start the excavation promptly after receiving the permit.