ARCFE GROUP 8 PROJECT PROGRESS

Oct 2018

75 Park Lane

As of Oct 12, 2018, window and Interior work has been progressed to the 13th floor.  The entire project is expected to be completed by the end of 2019.

Shore House

As of Sept 30th 2018, the interior work has been progressed to the 6th floor.  The entire project is expected to be complete by the end of 2018.

 

July 2018

75 Park Lane

As of July 2018, Superstructure concrete work is complete. MEP installation and interior wall layouts continue to progress on lower levels.  Interior work has been progressed substantially compared to last quarter.  The entire project is expected to be completed by the end of 2019.

Shore House

As of July 2018, superstructure concrete work and MEP installation is complete. Interior work has been substantially progressed to the 4th floor.  The entire project is expected to be complete by the end of 2018.

April 2018

 

75 Park Lane

As of April 2018, Superstructure concrete work is complete. MEP installation and interior wall layouts continue to progress on levels below newly poured floors.  Interior work has been progressed substantially compared to last quarter.

Shore House

As of April 2018, superstructure concrete work and MEP installation is complete. Interior work has been substantially progressed compared to last quarter.

December 2017

 

 

75 Park Lane

As of Nov 30, 2017, Superstructure concrete work is underway and has been poured up to the nineteenth floor. MEP installation and interior wall layouts continue to progress on levels below newly poured floors.

Shore House

As of Nov 30 2017, superstructure concrete work is underway and has been topped out. MEP installation is ongoing and interior wall layout continues on the 2nd floor.

September 2017

75 Park Lane

Superstructure concrete work is underway and has been poured up to the 9th  floor of the tower level. Tower logistics are in place and cycle times as sped up 1 day per floor.  Permanent MEP utility installation continues on the ground floor and interior wall layout has begun on the 2nd floor.

Shore House

Superstructure concrete work is underway and has been poured up to the 3rd floor. Concrete work is ongoing.

June 2017

75 Park Lane

As of the end of July, foundation activity for 75 Park Lane is finished. Superstructure concrete work is underway and has been poured up to the 2nd floor.

Shore House

As of the end of July, foundation activity for Shore House is finished. Superstructure concrete work is going to start.

March 2017

75 Park Lane:

Foundation activity for 75 Park Lane is ongoing. As of 2017Q1, the pile driving work is finished. Concrete pile caps and grade beams are being poured, and temporary electrical service is being installed.

2 Shore:

Foundation activity for Shore House is ongoing. As of 2017Q1, the pile driving work is finished. Concrete pile caps and grade beams are being poured, and temporary electrical service is being installed.

DECEMBER 2016

75 Park Lane

The construction for 75 Park Lane started in 2016Q4, and the foundation activity is ongoing. As of the end of Dec 2016, about 50% of piles were installed.

Shore House

The construction for Shore House started in 2016Q4, and the foundation activity is ongoing. As of the end of Dec 2016, about 15% of piles were installed.

OCTOBER 2016

75 Park Lane received foundation permit in early October. Strategic Capital held an official Ground Breaking Ceremony on 10/27/2016. On the day of ceremony, we saw that the excavation of 75 Park Lane has already started.

Developer told us that 2 Shore Drive North will receive its foundation permit in November. They will start the excavation promptly after receiving the permit.