Group 11 – Astoria project progress

[/spb_text_block] [/spb_column]
 
 

Dec 2020

 

    • As of Dec 2020,the project has finished the stairs and ramp on the  3rd, 4th, 5th and 6th floor and working on the 7th floor.

Nov 2019

 

    • As of July 2020,2/3 of foundation work has been finished and the remaining is schedule to finish in early Aug.  The sheet piling, pile cap and grade beam are all on schedule to be finished.

Nov 2019

    • As of Nov 2019,the Group 11 porject has completed dismantling all existing building, and the dismantle work has been signed off by DOB.  The design has been approved by DOB in June.  The underground water was checked.  At present, the project is waiting for the DoB’s foundation permit, expected to obtain in late Aug 2019.

Aug 2019

 

    • As of Aug 2019,the Group 11 porject has completed dismantling all existing building, and the dismantle work has been signed off by DOB.  The design has been approved by DOB in June.  The underground water was checked.  At present, the project is waiting for the DoB’s foundation permit, expected to obtain in late Aug 2019.

May 2019

 

 

    • As of May 2019,the Group 11 porject has completed dismantling all existing building, and the dismantle work has been signed off by DOB.  At present, the project is waiting for the DoB’s foundation permit.

Jan 2019

      • As of Jan 2019,the Group 11 porject has completed dismantling all existing building, and the dismantle work has been signed off by DOB.  At present, the project is waiting for the DoB’s foundation permit.  The foundation work is expected to start in Q2 2019.