Dec 2020
ARCFE GROUP 2
-This project has been completed.
Aug 2019
ARCFE GROUP 2
-This building is complete with temporary certificate of occupancy.
– Condo units are being sold and can be closed.
-The department of Finance has approved the title for each unit and the settlement is being proceeded.
Aug 2019
ARCFE GROUP 2
-This building is complete with temporary certificate of occupancy.
– Condo units are being sold and can be closed.
-The department of Finance has approved the title for each unit and the settlement is being proceeded.
May 2019
ARCFE GROUP 2
-This building is complete with temporary certificate of occupancy.
– Condo units are being sold and can be closed.
-The department of Finance has approved the title for each unit and the settlement is being proceeded.
Jan 2019
ARCFE GROUP 2
-This building is complete with temporary certificate of occupancy.
– Condo units are being sold and can be closed.
-The department of Finance has approved the title for each unit and the settlement is being proceeded.
Oct 2018
ARCFE GROUP 2
-This building is complete with temporary certificate of occupancy.
– Condo units are being sold and can be closed.
-The department of Finance has approved the title for each unit and the settlement is being proceeded.
April 2018
ARCFE GROUP 2
For our quarterly inspection, we went to check the job site in April 2018. A summary of project progress as follows:
-This building is complete with temporary certificate of occupancy.
– Condo units are being sold and a few owners have already moved in the building and in business.
-The department of Finance is currently in the process of preparing the title for each unit and the settlement will be proceeded when the title work is complete.
December 2017
ARCFE GROUP 2
For our quarterly inspection, we went to check the job site on December 14, 2017. A summary of project progress as follows:
-This building is complete with temporary certificate of occupancy.
-Condo units are being sold and a few owners have already moved in the building and in business.
September 2017
ARCFE GROUP 2
For our quarterly inspection, we went to check the job site on August 29, 2017. A summary of project progress as follows:
– There were a dozen of workers finishing up unit build-outs on ground floor. A couple of welders worked in garage. All unit build-out work on other floors was completed.
– One of elevators is operational and other one was not in service. Per parking engineer, automated parking garage is being tested now and is anticipated to be operational later this month.
– New sidewalk was paved and easement driveway and parking for adjacent property owners in rear paved was also paved.
– Right now, the GC is working to get signoffs from DOB.
Retail units build out shall wrap up later month. Now it is up to them how soon they can pull final CO.
June 2017
ARCFE GROUP 2
For our quarterly inspection, we went to check the job site on April 11, 2017. A summary of project progress as follows:
– There were 20 plus workers doing carpentry, sheetrock, storefront glass installation and painting from 1st to 3rd floors. Unit build-outs are progressing from 1st floor and 3rd floors. The GC will not handle any interior fit out for 4th and 5th floor. 6th to 9th floors are almost complete except some punch list items. .the project manager told me they would wrap up in two months.
– Panels installation is complete and windows are complete. Retail storefront window is being installed. Ground retail floor has been subdivided and interior fit out is ongoing. Per the project manager, it will be pharmacy in front and he does not know who other tenants are.
– Con Ed has recently provided to power to the building.
– The automate parking structure is still being set up however it looked more advance in setup as comparing to last site visit. Per the parking equipment site manager, they are looking to finishing up in two month and they would do an operational testing next month.
– CMU block wall in stairs have been painted thru out the building.
Overall, construction works are gradually progressing. Now it is very likely they will get their CO in June subject to completion of underground parking and subsequent sign off.