Oct 2019
Per quarterly site visit in April 2018, here is summary of finding:
– This building is complete and the temporary certificate of occupancy has been obtained.
– The units sold have been settled for occupancy.
April 2019
Per quarterly site visit in April 2018, here is summary of finding:
– This building is complete and the temporary certificate of occupancy has been obtained.
– The units sold have been settled for occupancy.
December 2017
Per quarterly site visit on Wed, 12/13/2017, here is summary of finding:
– This building is complete and is anticipated to obtain temporary certificate of occupancy.
– More than half of units (total 24) are sold and pending for closing as soon as TCO is issued.
September 2017
Per quarterly site visit on Wed, 10/4/2017, here is summary of finding:
– Construction is finished now and all appliances in except some refrigerators are not in and stoves pending hook up
– Laborers are painting the utility rooms and parking place.
– Apartments are appealing and roof view at the park and LIC and Manhattan is very appealing to buyers.
They are trying to get final signoff from building department currently. It should be ready in a month or two.
June 2017
Per quarterly site visit today June 26, 2017, here is summary of finding:
– Construction is near completion and workers are installing bathroom fixtures and kitchen appliances.
– Remaining works are in hallways, lobby, parking lots and gym room on roof. They are some minor works in apartments too.
– Windows, facade works and balcony plus railings are completed.
– Elevator has been completed on site but it is not yet operational.
– A model apartment unit has been set up by Modern Spaces on 3rd floor.