As of Dec 2021, the project has finished the stairs and ramp on the 3rd, 4th, 5th and 6th floor and is working on the 7th floor.the elevator has been installed, the roof waterproof production is in progress, the outer wall brick has reached the seventh layer, the inner wall plaster has been completed, the installation of the inner window has been completed, and the rough processing of the pipeline has been basically completed.