Group 12 – Jackson project progress

July 2023

  • Plumbing is underway throughout the building
  • Working on interior framing layouts and electrical riser
  • Exterior masonry is near completion
  • Trash chute is being installed
  • Elevator equipment is coming later this month
  • Curtain wall is in production

Apr 2023

  • Jackson Project Top Off

Dec 2022

  • Foundation completed on November 16th
  • Poured concrete on first floor on December 15th
  • Super structure phases going vertical
  • Utilities (water and sewage) brought in

Aug-Sep 2022

  • Early stages of foundation expected to be completed by end of Q4/2022

Mar 2022