Group 12 – Jackson project progress

Mar 2022

The Jackson Project construction has now resumed.

Dec 2021

By the end of December 2021, the above-ground structure of the Jackson Project has reached seven floors. Construction will resume in early 2022.

Aug 2019

  • The entire foundation work has been completed.
  • The superstructure has been built up to the second floor

May 2019

  • The project has been broke into ground since Q2 2018.
  • The foundation work has been 100% completed. Underpinning work has been completed.
  • The foundation piling has been completed

Jan 2019

  • The project has been broke into ground since Q2 2018.
  • The foundation work has been 100% completed. Underpinning work has been completed.
  • The foundation piling has been completed

Oct 2018

  • The project has been broke into ground since Q2 2018.
  • The foundation work has been 70% completed. Underpinning work has been performed.
  • The foundation piling has been scheduled to be conducted

Jul 2018

  • The project has been broke into ground since Q2 2018.
  • The foundation work has been started

Dec 2017

  • The site is being prepared and expected to be ready for construction New Year in early January.
  • All safety monitoring devices recently installed on adj buildings and underground MTA tunnel.
  • At the same time, the contractor Lions group is in processing of pulling work permit

Sep 2017

  • Project insurance package has been approved by MTA;
  • 3 manual vibration monitor sensor have been installed on MTA tunnels;
  • Based on DOB, the developer has revised their site safety plan accordingly and expects to pull SOE permit in October

Jun 2017

Demolition work had been completed earlier this year and received sign-off from DOB. Currently, contractor is waterproofing adjacent buildings’ exterior walls.  Lions group, our GC, is working diligently to pull work permit for the project. They target to break ground in late July or early August.

Mar 2017

Per site visit on 2/20/17, here is summary of finding:

  • building structure is down to basement and they will finish up this week;
  • about 15 worker on site and waterproofing is done mostly to ground;
  • currently the contractor and scaffold company working to remove building violation regarding sidewalk bridge’s sign before they remove scaffolding bridge.

Overall, the construction has been progressing since last quarter.

Dec 2016

On the site visit day, demolition progress is picking up since the last visit. 27-49 Jackson’s 2nd floor structure is almost removed and demolition at 27-51 Jackson Ave is down to ground floor. We should bring down all above-grade structures next week. We will finish it in two week if everything goes smoothly.

Oct 2016

Till 10/20/2016, demolition permit on old building has been approved. The general contractor has finished building up safety fence. Demolition is ready to go.

Dec 2015

It is expected to obtain work permit to start demolishing Jackson building in January 2016.

Jun 2015

The general contractors are preparing to apply for work permit to start demolishing the old building in Jackson apartment.