GROUP 13 – 38th Ave & Thomson Project Progress

Sep 2023

38th Ave

  • Construction progressing on schedule with current 5th Floor completion this month;
  • Continue to project completion by the 4th Quarter of 2024

Jul 2023

38th Ave

  • Commencing superstructure
  • Top off expected in Q3 of 2023
  • Expected completion at the end of 2024

Apr 2023

38th Ave

  • Construction site is active with SOE (Support with Excavation) activity in full operation
  • Expect to complete SOE by mid-May
  • Excavation is scheduled to commence immediately following before the end of May
  • Pouring concrete footings/forms will follow with foundation expected to commence in June

Thomson

  • CO obtained in Fall 2022
  • Residents have moved in

Sep 2022

Thomson

  • Construction is completed.
  • CO obtained for lower floors of rental units. Applied for CO for upper floors.
  • Earliest move in date is set for September 15th.

Aug 2022

Thomson

  • Substantial completion expected by end of this month
  • TCO to be applied next month
  • Launched to the market on August 16th

38th Ave

  • Pre-construction & development efforts continue with expected construction commenced by end of Q4/2022

June 2022

Thomson

38th Ave

  • Break ground ceremony held on June 14th.