Astoria组11项目进展(archive)

[spb_row element_name=”Row” wrap_type=”content-width” parallax_image_height=”content-height” parallax_image_movement=”fixed” parallax_image_speed=”0.5″ bg_video_loop=”yes” parallax_video_height=”window-height” parallax_video_overlay=”none” row_overlay_opacity=”0″ vertical_center=”false” width=”1/1″ el_position=”first last”] [spb_column col_bg_type=”cover” col_parallax_image_movement=”fixed” col_parallax_image_speed=”0.5″ col_padding=”0″ col_animation=”none” col_animation_delay=”0″ width=”1/4″ el_position=”first”] [spb_text_block title=”2020年12月” animation=”none” animation_delay=”0″ padding_vertical=”0″ padding_horizontal=”0″ width=”1/1″ el_position=”first last”]

  • 招募进行中,I-526已获批
  • 工程进度

截止到2020年12月底,组十一项目进展顺利,已完成3、4、5、6层的楼梯和ramp,目前正在做7层的模版。

[/spb_text_block] [/spb_column] [spb_column width=”3/4″ el_position=”last”] [spb_gallery gallery_id=”18740″ display_type=”masonry” columns=”3″ fullwidth=”no” gutters=”no” image_size=”thumbnail” slider_transition=”slide” show_thumbs=”yes” autoplay=”yes” show_captions=”no” enable_lightbox=”yes” width=”1/1″ el_position=”first last”] [/spb_column] [/spb_row] [spb_row element_name=”Row” wrap_type=”content-width” parallax_image_height=”content-height” parallax_image_movement=”fixed” parallax_image_speed=”0.5″ bg_video_loop=”yes” parallax_video_height=”window-height” parallax_video_overlay=”none” row_overlay_opacity=”0″ vertical_center=”false” minimize_row=”yes” width=”1/1″ el_position=”first last”] [spb_column col_bg_type=”cover” col_parallax_image_movement=”fixed” col_parallax_image_speed=”0.5″ col_padding=”0″ col_animation=”none” col_animation_delay=”0″ width=”1/4″ el_position=”first”] [spb_text_block title=”2020年7月” animation=”none” animation_delay=”0″ padding_vertical=”0″ padding_horizontal=”0″ width=”1/1″ el_position=”first last”]

  • 招募进行中,I-526已获批
  • 工程进度

截止到2020年7月,组十一项目已完成foundation的2/3工程,sheet pile, pile cap和grade beam都进展顺利,预计foundation工程2周后(8月初)可以全部完成。

[/spb_text_block] [/spb_column] [spb_column width=”3/4″ el_position=”last”] [spb_gallery gallery_id=”18682″ display_type=”masonry” columns=”3″ fullwidth=”no” gutters=”no” image_size=”thumbnail” slider_transition=”slide” show_thumbs=”yes” autoplay=”yes” show_captions=”no” enable_lightbox=”yes” width=”1/1″ el_position=”first last”] [/spb_column] [/spb_row] [spb_row element_name=”Row” wrap_type=”content-width” parallax_image_height=”content-height” parallax_image_movement=”fixed” parallax_image_speed=”0.5″ bg_video_loop=”yes” parallax_video_height=”window-height” parallax_video_overlay=”none” row_overlay_opacity=”0″ vertical_center=”false” minimize_row=”yes” width=”1/1″ el_position=”first last”] [spb_column col_bg_type=”cover” col_parallax_image_movement=”fixed” col_parallax_image_speed=”0.5″ col_padding=”0″ col_animation=”none” col_animation_delay=”0″ width=”1/4″ el_position=”first”] [spb_text_block title=”2019年11月” animation=”none” animation_delay=”0″ padding_vertical=”0″ padding_horizontal=”0″ width=”1/1″ el_position=”first last”]

  • 招募进行中,I-526正在审理
  • 工程进度

截止到2019年11月,组十一项目已完成了全部拆除工作并由房屋管理局正式验收(sign off),并且项目图纸已获DOB批准,地下水检测已完成。目前,建筑围栏已经做好,正在做开工前的准备。

[/spb_text_block] [/spb_column] [spb_column width=”3/4″ el_position=”last”] [spb_gallery gallery_id=”18521″ display_type=”masonry” columns=”3″ fullwidth=”no” gutters=”no” image_size=”thumbnail” slider_transition=”slide” show_thumbs=”yes” autoplay=”yes” show_captions=”no” enable_lightbox=”yes” width=”1/1″ el_position=”first last”] [/spb_column] [/spb_row] [spb_row element_name=”Row” wrap_type=”content-width” parallax_image_height=”content-height” parallax_image_movement=”fixed” parallax_image_speed=”0.5″ bg_video_loop=”yes” parallax_video_height=”window-height” parallax_video_overlay=”none” row_overlay_opacity=”0″ vertical_center=”false” minimize_row=”yes” width=”1/1″ el_position=”first last”] [spb_column col_bg_type=”cover” col_parallax_image_movement=”fixed” col_parallax_image_speed=”0.5″ col_padding=”0″ col_animation=”none” col_animation_delay=”0″ width=”1/4″ el_position=”first”] [spb_text_block title=”2019年5月” animation=”none” animation_delay=”0″ padding_vertical=”0″ padding_horizontal=”0″ width=”1/1″ el_position=”first last”]

 

  • 招募进行中,I-526正在审理
  • 工程进度

截止到2019年5月,组十一项目已完成了全部拆除工作并由房屋管理局正式验收(sign off)。目前,项目正在申请地基开工许可证。

[/spb_text_block] [/spb_column] [spb_column width=”3/4″ el_position=”last”] [spb_gallery gallery_id=”17843″ display_type=”masonry” columns=”3″ fullwidth=”no” gutters=”no” image_size=”thumbnail” slider_transition=”slide” show_thumbs=”yes” autoplay=”yes” show_captions=”no” enable_lightbox=”yes” width=”1/1″ el_position=”first last”] [/spb_column] [/spb_row] [spb_row element_name=”Row” wrap_type=”content-width” parallax_image_height=”content-height” parallax_image_movement=”fixed” parallax_image_speed=”0.5″ bg_video_loop=”yes” parallax_video_height=”window-height” parallax_video_overlay=”none” row_overlay_opacity=”0″ vertical_center=”false” minimize_row=”yes” width=”1/1″ el_position=”first last”] [spb_column col_bg_type=”cover” col_parallax_image_movement=”fixed” col_parallax_image_speed=”0.5″ col_padding=”0″ col_animation=”none” col_animation_delay=”0″ width=”1/4″ el_position=”first”] [spb_text_block title=”2019年1月” animation=”none” animation_delay=”0″ padding_vertical=”0″ padding_horizontal=”0″ width=”1/1″ el_position=”first last”]

  • 招募进行中,I-526正在审理
  • 截止到2019年1月,美国创业区域中心的组十一项目已完成所有拆除工作,并由房屋管理局正式验收(sign off)。目前,项目正在申请地基的开工许可,预计2019年二季度开始地基工作。

[/spb_text_block] [/spb_column] [spb_column width=”3/4″ el_position=”last”] [spb_gallery gallery_id=”18204″ display_type=”masonry” columns=”4″ fullwidth=”no” gutters=”no” image_size=”thumbnail” slider_transition=”slide” show_thumbs=”yes” autoplay=”yes” show_captions=”no” enable_lightbox=”yes” width=”1/1″ el_position=”first last”] [/spb_column] [/spb_row]