[spb_row element_name=”Row” wrap_type=”content-width” parallax_image_height=”content-height” parallax_image_movement=”fixed” parallax_image_speed=”0.5″ bg_video_loop=”yes” parallax_video_height=”window-height” parallax_video_overlay=”none” row_overlay_opacity=”0″ vertical_center=”true” width=”1/1″ el_position=”first last”] [spb_gallery gallery_id=”18854″ display_type=”masonry” columns=”2″ fullwidth=”no” gutters=”yes” image_size=”thumbnail” slider_transition=”slide” show_thumbs=”yes” autoplay=”yes” show_captions=”no” enable_lightbox=”yes” width=”1/1″ el_position=”first last”] [spb_text_block element_name=”Dec 2020″ animation=”none” animation_delay=”0″ padding_vertical=”0″ padding_horizontal=”0″ width=”1/1″ el_position=”first last”]
Dec 2020
As of Dec 2020, the project has finished the stairs and ramp on the 3rd, 4th, 5th and 6th floor and is working on the 7th floor.
[/spb_text_block] [/spb_row] [spb_row element_name=”Row” wrap_type=”content-width” parallax_image_height=”content-height” parallax_image_movement=”fixed” parallax_image_speed=”0.5″ bg_video_loop=”yes” parallax_video_height=”window-height” parallax_video_overlay=”none” row_overlay_opacity=”0″ vertical_center=”false” minimize_row=”no” width=”1/1″ el_position=”first last”] [spb_gallery gallery_id=”18682″ display_type=”masonry” columns=”2″ fullwidth=”no” gutters=”yes” image_size=”thumbnail” slider_transition=”slide” show_thumbs=”yes” autoplay=”yes” show_captions=”no” enable_lightbox=”yes” width=”1/1″ el_position=”first last”] [spb_text_block animation=”none” animation_delay=”0″ padding_vertical=”0″ padding_horizontal=”0″ width=”1/1″ el_position=”first last”]
July 2020
As of July 2020,2/3 of foundation work has been finished and the remaining is schedule to finish in early Aug. The sheet piling, pile cap and grade beam are all on schedule to be finished.
[/spb_text_block] [/spb_row] [spb_row element_name=”Row” wrap_type=”content-width” parallax_image_height=”content-height” parallax_image_movement=”fixed” parallax_image_speed=”0.5″ bg_video_loop=”yes” parallax_video_height=”window-height” parallax_video_overlay=”none” row_overlay_opacity=”0″ vertical_center=”false” minimize_row=”no” width=”1/1″ el_position=”first last”] [spb_gallery gallery_id=”18521″ display_type=”masonry” columns=”3″ fullwidth=”no” gutters=”yes” image_size=”thumbnail” slider_transition=”slide” show_thumbs=”yes” autoplay=”yes” show_captions=”no” enable_lightbox=”yes” width=”1/1″ el_position=”first last”] [spb_text_block animation=”none” animation_delay=”0″ padding_vertical=”0″ padding_horizontal=”0″ width=”1/1″ el_position=”first last”]
Nov 2019
As of Nov 2019,the Group 11 porject has completed dismantling all existing building, and the dismantle work has been signed off by DOB. The design has been approved by DOB in June. The underground water was checked. At present, the project is waiting for the DoB’s foundation permit, expected to obtain in late Aug 2019.
[/spb_text_block] [/spb_row] [spb_row element_name=”Row” wrap_type=”content-width” parallax_image_height=”content-height” parallax_image_movement=”fixed” parallax_image_speed=”0.5″ bg_video_loop=”yes” parallax_video_height=”window-height” parallax_video_overlay=”none” row_overlay_opacity=”0″ vertical_center=”false” minimize_row=”no” width=”1/1″ el_position=”first last”] [spb_gallery gallery_id=”18435″ display_type=”masonry” columns=”3″ fullwidth=”no” gutters=”yes” image_size=”thumbnail” slider_transition=”slide” show_thumbs=”yes” autoplay=”yes” show_captions=”no” enable_lightbox=”yes” width=”1/1″ el_position=”first last”] [spb_text_block animation=”none” animation_delay=”0″ padding_vertical=”0″ padding_horizontal=”0″ width=”1/1″ el_position=”first last”]
As of Aug 2019
As of Aug 2019,the Group 11 porject has completed dismantling all existing building, and the dismantle work has been signed off by DOB. The design has been approved by DOB in June. The underground water was checked. At present, the project is waiting for the DoB’s foundation permit, expected to obtain in late Aug 2019.
[/spb_text_block] [/spb_row] [spb_row element_name=”Row” wrap_type=”content-width” parallax_image_height=”content-height” parallax_image_movement=”fixed” parallax_image_speed=”0.5″ bg_video_loop=”yes” parallax_video_height=”window-height” parallax_video_overlay=”none” row_overlay_opacity=”0″ vertical_center=”false” minimize_row=”no” width=”1/1″ el_position=”first last”] [spb_gallery gallery_id=”18854″ display_type=”masonry” columns=”3″ fullwidth=”no” gutters=”yes” image_size=”thumbnail” slider_transition=”slide” show_thumbs=”yes” autoplay=”yes” show_captions=”no” enable_lightbox=”yes” width=”1/1″ el_position=”first last”] [spb_text_block element_name=”May 2019″ animation=”none” animation_delay=”0″ padding_vertical=”0″ padding_horizontal=”0″ width=”1/1″ el_position=”first last”]
May 2019
As of May 2019,the Group 11 porject has completed dismantling all existing building, and the dismantle work has been signed off by DOB. At present, the project is waiting for the DoB’s foundation permit.
[/spb_text_block] [/spb_row] [spb_row element_name=”Row” wrap_type=”content-width” parallax_image_height=”content-height” parallax_image_movement=”fixed” parallax_image_speed=”0.5″ bg_video_loop=”yes” parallax_video_height=”window-height” parallax_video_overlay=”none” row_overlay_opacity=”0″ vertical_center=”false” minimize_row=”no” width=”1/1″ el_position=”first last”] [spb_gallery gallery_id=”18204″ display_type=”masonry” columns=”4″ fullwidth=”no” gutters=”yes” image_size=”thumbnail” slider_transition=”slide” show_thumbs=”yes” autoplay=”yes” show_captions=”no” enable_lightbox=”yes” width=”1/1″ el_position=”first last”] [spb_text_block element_name=”Jan 2019″ animation=”none” animation_delay=”0″ padding_vertical=”0″ padding_horizontal=”0″ width=”1/1″ el_position=”first last”]
Jan 2019
As of Jan 2019,the Group 11 porject has completed dismantling all existing building, and the dismantle work has been signed off by DOB. At present, the project is waiting for the DoB’s foundation permit. The foundation work is expected to start in Q2 2019.