​Murray Central

Project Progress

Project A

August 2024

  • Project A is expected to commence excavation in September 2024.

  • Expected completion in December 2026, with TCO obtain in January 2027.

Project B

August 2024

  • Project B is currently in their final stages of superstructure, and expected to top out in the next few months.