Group A

One Murray Park

Project progress

One Murray Park

Apr 2018

Per quarterly site visit in April 2018, here is summary of finding:

- This building is complete and the temporary certificate of occupancy has been obtained.

- The units sold have been settled for occupancy.

Dec 2017

Per quarterly site visit on Wed, 12/13/2017, here is summary of finding:

- This building is complete and is anticipated to obtain temporary certificate of occupancy.

- More than half of units (total 24) are sold and pending for closing as soon as TCO is issued.

Sep 2017

Per quarterly site visit on Wed, 10/4/2017, here is summary of finding:

- Construction is finished now and all appliances in except some refrigerators are not in and stoves pending hook up

- Laborers are painting the utility rooms and parking place.

- Apartments are appealing and roof view at the park and LIC and Manhattan is very appealing to buyers.

They are trying to get final sign off from building department currently. It should be ready in a month or two.

Jun 2017

Per quarterly site visit today June 26, 2017, here is summary of finding:

- Construction is near completion and workers are installing bathroom fixtures and kitchen appliances.

- Remaining works are in hallways, lobby, parking lots and gym room on roof. They are some minor works in apartments too.

- Windows, facade works and balcony plus railings are completed.

- Elevator has been completed on site but it is not yet operational.

- A model apartment unit has been set up by Modern Spaces on 3rd floor.

Mar 2017

Murray Park North:

Construction of Murray Park North was completed in 2016 Q3. Buyers have moved in.

Murray Park South:

Per quarterly site visit on March 17, 2017, here is summary of finding:

- a dozen of construction workers doing interior finished works including tiles, carpentry, patching, painting.

- at time of site visit, Pane stone truck was offloading tiles to job site.

- windows, facade works and balcony plus railings are completed except 1st floor

- almost all sheetrock works and drywall are done except 1st floor, bedrooms, living rooms, bathrooms are near completion.

- wood floors and kitchen related works have not commenced yet. light and plumbing fixtures have not installed yet. We believe they will begin flooring and kitchen work very soon.

- elevator has been completed on site but it is not yet operational.

Contractor should finish up the building’s interior in three to five months depending on manpower on job site.