top of page
dining2_gray2030.jpg

Group 4

Broadway/Jackson Project progress

Broadway/Jackson

Aug 2022

The 8th floor of the building is under construction

Mar 2022

The Jackson Project construction has now resumed.

Dec 2021

The above-ground structure of the Jackson Project has reached seven floors. Construction will resume in early 2022. The Broadway project has been fully completed and commissioned. I-526 has been approved.

Dec 2020

Broadway is finished

Jackson is under construction

Nov 2019

In Nov 2019, ARCFE project management team went to the job site to inspect the project and check out the project progress as follows:

Broadway Project

- TCO has been obtained in Nov 2018.

- Leasing has started and some tenants have moved in.

Jackson Project

- The entire foundation work has been completed.

- The superstructure has been built up to the seventh floor.

Aug 2019

In Aug 2019, ARCFE project management team went to the job site to inspect the project and check out the project progress as follows:

Broadway Project

- TCO has been obtained in Nov 2018.

- Leasing has started and some tenants have moved in.

Jackson Project

- The entire foundation work has been completed.

- The superstructure has been built up to the second floor.

May 2019

In May 2019, ARCFE project management team went to the job site to inspect the project and check out the project progress as follows:

Broadway Project

- TCO has been obtained in Nov 2018.

- Leasing has started and some tenants have moved in.

Jackson Project

- The project has been broke into ground since Q2 2018.

- The foundation work has been 100% completed. Underpinning work has been completed.

- The foundation piling has been completed.