top of page
The+Jackson_2nd+floor+kitchen+living+room.jpg

Group 11 Pianist

Project Progress

Pianist

May 2023

I-526 approved

As of May 2023, Group 11 "Pianist" project construction has been completed.

The project is expected to obtain TCO in mid-June.

Total of 69 units: 45 are leased by Nest Seeker, and 24 are affordable units leased out by the government.

All units are expected to be fully leased out by the end of August 2023.

Aug 2022

I-526 approved

Substantial completion by end of Q4 of 2022 with TCO followed shortly thereafter

Floors are finished

AC is installed

May 2022

As of this writing, the building's façade and glass curtain wall have been completed, and the scaffolding is being removed in an orderly manner. The plumbing, thermal insulation and thermal insulation of the building have been completed, the partition of the apartment unit has been completed, and the stage of fine decoration has begun. It is expected that the project TCO will be obtained in the summer of 2022 and will be delivered before the end of the year.

Dec 2021

As of Dec 2021, the project has finished the stairs and ramp on the 3rd, 4th, 5th and 6th floor and is working on the 7th floor.the elevator has been installed, the roof waterproof production is in progress, the outer wall brick has reached the seventh layer, the inner wall plaster has been completed, the installation of the inner window has been completed, and the rough processing of the pipeline has been basically completed.

Jun 2021

By the end of June 2021, the main structure of the project has been capped, the elevator installation of the project has been completed, the exterior wall is more than half constructed, and the low-floor glass curtain wall is ready to be installed.