Davis
Nov 2023
Topped out, expected completion Quarter 1 of 2025
Sep 2023
Construction build out progressing; with projected completion by mid 2024
Jul 2023
As of July 2023, the Davis Project is moving on schedule.
Fourth floor construction has been completed.
Construction of the fifth floor is undergoing.
The project's developer ZD JASPER is aiming to complete construction of one floor per week.
May 2023
Apr 2023
Foundation work has begun
Excavation has nearly completed and crews are in the process of forming the reinforced concrete perimeter walls as the site fills up with a network of steel rebar for the floors, columns, and walls.
Based on the pace of progress, Davis project could begin to rise above street level near the end of spring and top out by the end of 2023.
Union
Nov 2023
Broke ground
Sep 2023
Continued site work and preparation
Excavation equipment to be delivered by the end of this month
July 2023
Site preparation is expected to commence in the following weeks
The developer has obtained fence permit, groundwork permit, and foundation permit