Group 14 DAVIS/UNION

Project Progress

Davis

Nov 2023

Topped out, expected completion Quarter 1 of 2025

Sep 2023

Construction build out progressing; with projected completion by mid 2024

Jul 2023

As of July 2023, the Davis Project is moving on schedule.

Fourth floor construction has been completed.
 

Construction of the fifth floor is undergoing.

The project's developer ZD JASPER is aiming to complete construction of one floor per week.

May 2023

Apr 2023

Foundation work has begun

Excavation has nearly completed and crews are in the process of forming the reinforced concrete perimeter walls as the site fills up with a network of steel rebar for the floors, columns, and walls.

 

Based on the pace of progress, Davis project could begin to rise above street level near the end of spring and top out by the end of 2023.

Union

Nov 2023

Broke ground

Sep 2023

Continued site work and preparation

Excavation equipment to be delivered by the end of this month

July 2023

Site preparation is expected to commence in the following weeks

The developer has obtained fence permit, groundwork permit, and foundation permit 