Group 16

Astoria Rowan II

Project Progress

Astoria Rowan II

May 2026

The project is 57% complete overall. The main structure is finished, and MEP and finishingwork are now in full swing:


 Main Structure: The concrete superstructure has been fully topped out, with only asmall amount of stair work remaining. Formwork and shoring have been removed.


MEP & Finishing: Plumbing, sprinkler, electrical, and HVAC systems are advancingconcurrently up to Levels 6-7. Elevator equipment has been delivered and is beinginstalled. Wall framing and gypsum board work are progressing on Levels 2-7. Tileinstallation has commenced in bathrooms on Level 4. Rough-in for electrical andplumbing trim- out is proceeding in an orderly manner.


Safety & Management: The construction hoist is in place. Off-site storage of windowmaterials is sufficient, ensuring smooth progress.

Feb 2026

The project is 55% complete overall, with main structure construction being finalized:
 

Structure & Framing: The concrete superstructure is substantially complete. Floor slab pours are finished on Level 7 and the roof, with only a small number of stair sections
remaining. Interior wall framing is progressing in an orderly manner on Levels 2–6.

 

Specialty Construction: Cast iron plumbing risers are installed on Level 5 and below, with branch piping underway on Levels 2–4. Electrical branch wiring has commenced on Level 3. Building risers have been installed up to the roof level.

 

Safety & Management: The site operates under fully enclosed, standardized management. The construction hoist is being installed. On-site materials are properly stored.

Nov 2025

Overall Progress: The project, a 7-story mixed-use building (including a basement level), is 30% complete and progressing on schedule.

Foundation Work Nearing Completion: All perimeter concrete foundations, internal column footings and pillars, as well as concrete foundation walls have been completed. The first-floor concrete slab has been poured, and access stairs to the basement have been constructed.

Critical Supporting Work Underway: Drainage sleeve installation on the first floor is finished. Next steps include advancing the superstructure to Floors 2–3, installing sidewalk bridging, and commencing vertical extension of the main structure.

May 2024

Project topped out in Q4/2023.

The exterior scaffolding of the building are being dismantled.

 

Interior construction is undergoing.

Sales office is ready, first round of sales is set to begin in the summer.

ARCFE
new badges 3.png
Get in touch
28-07 Jackson Ave, 8th Floor
Long Island City NY 11101


 
  • Facebook
  • LinkedIn
  • Youtube

No offer to sell any security is made by this website. The information on this web site is not an offer to sell or solicitation of an offer to buy an interest in any investment or for the provision of any investment management or advisory services. Any such offer or solicitation will be pursuant to exemptions from registration requirements set out in applicable securities laws and made only by means of delivery of a confidential private offering memorandum relating to a particular investment to qualified investors in those jurisdictions where permitted by law.

bottom of page