Astoria Rowan II
Nov 2025
Overall Progress: The project, a 7-story mixed-use building (including a basement level), is 30% complete and progressing on schedule.
Foundation Work Nearing Completion: All perimeter concrete foundations, internal column footings and pillars, as well as concrete foundation walls have been completed. The first-floor concrete slab has been poured, and access stairs to the basement have been constructed.
Critical Supporting Work Underway: Drainage sleeve installation on the first floor is finished. Next steps include advancing the superstructure to Floors 2–3, installing sidewalk bridging, and commencing vertical extension of the main structure.