Brooklyn Gowanus
Dec 2024
The project was completed and commenced leasing in December 2024.
As of July 2026, it is in its second leasing cycle.
Aug 2024
Exterior facade brick work near completion.
Windows 50% installed.
Substantial near completion with sheetrock.
Tiles installation well underway.
Plastering well underway.
Mechanical done.
Roofing 60% completed.
Project construction around 80% completed.