Group 19 Brooklyn Gowanus

Project Progress

Brooklyn Gowanus

Aug 2024

Exterior facade brick work near completion.

​

Windows 50% installed.

​

Substantial near completion with sheetrock.

​

Tiles installation well underway.

​

Plastering well underway.

​

Mechanical done.

​

Roofing 60% completed.

​

Project construction around 80% completed.

May 2024

Construction progress is moving on time as plan.

 

Construction reached 7th floor was of May 10th, 2024.