Project A

Nov 2025

Overall Progress: The project is currently 68% complete. The superstructure is fully finished, and work has transitioned to the interior/exterior finishing and systems installation phase.

North & South Tower Progress: Exterior wall and window installation in the North Tower is nearly complete, with interior finishing (painting, leveling) now underway. In the South Tower, exterior wall and window installation is also nearly complete, and interior framing work is actively progressing.

Systems Work: Rough-in work for MEP (Mechanical, Electrical, Plumbing), fire protection, and electrical systems is proceeding throughout the building. These systems are nearly complete in the North Tower. One elevator in the North Tower has passed inspection for construction use.

Support & Safety: Trash chutes have been installed in both towers, and roof work is advancing. All hoists are fully operational, and temporary fencing, fall protection, and other necessary safety measures are in place.

Aug 2024

Stop work order has been lifted, construction work is now resumed.

Foundation work on-going, expected completion early November.

Dec 2023

Project had its break ground ceremony on Dec 19th, 2023.

Oct 2023

Project has topped out.

Urban 21

Nov 2025

The project continues to progress steadily and is on track for full completion by the end of this year, with the Temporary Certificate of Occupancy (TCO) expected to be obtained in early 2026.

The building, named "Urban 21," has seen strong sales performance, achieving a 70% sales rate to date. Market response remains highly positive.

Aug 2024

Condos are 60% sold.

The framing of all condominium units has been completed.

The installation of sheetrock has begun and is expected to completed one floor a week.

Window framing has been fully completed and window installation is expected to begin at the end of August.

Construction of the exterior walls and glazing expected to be completed by mid-October;

Both residential elevators are in place;

Sprinklers have been installed from the 2nd floor to 9th floor;

Bathtubs for all condominium units have arrived and have been installed up to the 6th floor.

Dec 2023

Project has topped out.

Oct 2023

Project had its break ground ceremony on Dec 19th, 2023.

Logo with name white.png
arcfe-badges_all white_edited.png
arcfe-badges_all white_edited.png
Get in touch
28-07 Jackson Ave, 8th Floor
Long Island City NY 11101


 
  • Facebook
  • LinkedIn
  • Youtube

No offer to sell any security is made by this website. The information on this web site is not an offer to sell or solicitation of an offer to buy an interest in any investment or for the provision of any investment management or advisory services. Any such offer or solicitation will be pursuant to exemptions from registration requirements set out in applicable securities laws and made only by means of delivery of a confidential private offering memorandum relating to a particular investment to qualified investors in those jurisdictions where permitted by law.

bottom of page