top of page
10_Rooftop_Garden.webp

Group 8 Park Shore

Project Progress

Park Shore

May 2020

75 Park Lane:

- As of Jan 2020, the construction has been completed. Since then, buyers started closing their purchases and moved in.

Shore House:

- As of Nov 2019, the construction is completed and the project is finished. Buyers have moved in.

Nov 2019

75 Park Lane:

- As of Nov 2019, the construction has been almost completed with some remaining punch list items. Buyers have received the notice from the developer to prepare for closing in late Dec 2019.

Shore House:

- As of Nov 2019, the construction is completed and the project is finished.

Jul 2019

75 Park Lane:

- As of July 2019, the construction has been made rapid progress till the top Floor. The entire project is expected to be completed by the end of 2019. The pre-sale has been over 75%+.

Shore House:

- As of July 2019, the construction is completed and the TCO has been obtained. Pre-sold units started to be closed and buyers moved in.

Apr 2019

75 Park Lane:

- As of March 28, the construction has been made rapid progress till the 34th Floor. The entire project is expected to be completed by Oct 2019. The pre-sale has been over 70%.

Shore House:

- As of March 28, 2019, the construction is completed and the TCO has been obtained. Pre-sold units can be closed soon.

Jan 2019

75 Park Lane:

- As of Jan 2019, the construction has been made rapid progress. The entire project is expected to be completed by the end of 2019. The pre-sale has been over 60%.

Shore House:

- As of Jan 2019, the construction is close to be completed. The TCO is expected to be obtained in the first half of 2019 and pre-ale buyers can move in right after TCO.