38th Ave
May 2024
Delivery of materials are on time. Installation is commenced.
Framing will be completed, sheetrock will be installed.
Plumbing and electrical will continue being installed.
Once the connections are ready, installation of appliances will be commenced.
Construction expected to complete at the end of 2024.
Nov 2023
Topped out
Expected completion Quarter 4 of 2024
Sep 2023
Construction progressing on schedule with current 5th Floor completion this month
Continue to project completion by the 4th Quarter of 2024
Apr 2023
Construction site is active with SOE (Support with Excavation) activity in full operation
Expect to complete SOE by mid-May
Excavation is scheduled to commence immediately following before the end of May
Pouring concrete footings/forms will follow with foundation expected to commence in June